drozwood90
Senior Member
OK, the situation is:
I have a new home being built. The builder told me that I was able to make changes for 2 weeks. After that, it would be a $250 charge per change.
So, within 2 days, I came up with all my changes. They took their sweet time approving things. 3+ weeks later they approved most things.
However, there were 2 things that did NOT get any attention, and I think they thought I would forget about it. On that second day, I asked to contact the electrician and plumber regarding how they were going to run the plumbing and how they were going to run the electrical. I was told "to code"....which bothers me as "to code" a few years ago allowed for aluminum wiring in the house! Anywhoo...as I had asked to speak to them, and this was never addressed, until AFTER my 2 week period, I think the builder is "pissed" and just does not want to make any more changes, especially now that they can not get their $250!
The reason:
After speaking to the plumber, I asked for a separate drop to go to the washer/dryer area up on the second floor (we moved the washer and dryer upstairs), instead of him taping into the bathroom pipes that are right next to it. The next item, was to make certain that the feeder lines are all 3/4". Even the lines coming out of the hot water tank. The plumber indicated to me that the 3/4" line was about a $10 change. The extra drop wouldn't be more then $500. OK, even if the builder 2x the charges, I'm still happy with that price. They came back with $3100!!! My guess is, they 10x the price!
The electrician told me that he knows what I wanted, and he went through line item by line item, and gave the builder a new quote. The builder came back with $7100! WHAT? I figured on $2k-3k. As there would be maybe 3x the copper wire, and effort to pull the wire. The best part was, on BOTH of these quotes, the builder would not give me a breakdown on HOW the price got there. They said, they never got a breakdown...even though the electrician told me that they went through everything line item by line item.
The question:
The plumbing:
Was a nice to have. If they do not want to do thats fine.
The electrical:
They are going to put 12 plugs per breaker. This means in my new 40 breaker panel (which I paid extra for), I am going to get 16 breakers.
So, this means, all the bedroom plugs will all be tied together. The kitchen will have two stripes of plugs in it, instead of every other plug being a different circuit. That is, you have 2 walls
Their way:
wall one, has circuit A then A, wall two has circuit B then B.
My way:
wall one, has circuit A then B, wall two has circuit B then A.
Each bedroom should be on it's own circuit. So, what I have asked them to do, is loop the wires. For each plug in the kitchen, tie them together in the basement. For each other room, loop them together into the attic, or through the floor into the basement (two floor home).
If they will not do this. What are my options?
I think I should drag wires on the weekend when they are not there (they told me I can't work on the house during the build)? If I do, how do I make sure it will pass inspection? If I do not touch ANY of their wiring, I don't think they can complain. However, Can I drag a wire, leave a service loop and put it in the junction box and just tape the end. Leave it dead? Should I try to drag it all the way to my panel? Should I just leave it going to a junction box in the attic/basement?
Any other suggestions?
--Dan
I have a new home being built. The builder told me that I was able to make changes for 2 weeks. After that, it would be a $250 charge per change.
So, within 2 days, I came up with all my changes. They took their sweet time approving things. 3+ weeks later they approved most things.
However, there were 2 things that did NOT get any attention, and I think they thought I would forget about it. On that second day, I asked to contact the electrician and plumber regarding how they were going to run the plumbing and how they were going to run the electrical. I was told "to code"....which bothers me as "to code" a few years ago allowed for aluminum wiring in the house! Anywhoo...as I had asked to speak to them, and this was never addressed, until AFTER my 2 week period, I think the builder is "pissed" and just does not want to make any more changes, especially now that they can not get their $250!
The reason:
After speaking to the plumber, I asked for a separate drop to go to the washer/dryer area up on the second floor (we moved the washer and dryer upstairs), instead of him taping into the bathroom pipes that are right next to it. The next item, was to make certain that the feeder lines are all 3/4". Even the lines coming out of the hot water tank. The plumber indicated to me that the 3/4" line was about a $10 change. The extra drop wouldn't be more then $500. OK, even if the builder 2x the charges, I'm still happy with that price. They came back with $3100!!! My guess is, they 10x the price!
The electrician told me that he knows what I wanted, and he went through line item by line item, and gave the builder a new quote. The builder came back with $7100! WHAT? I figured on $2k-3k. As there would be maybe 3x the copper wire, and effort to pull the wire. The best part was, on BOTH of these quotes, the builder would not give me a breakdown on HOW the price got there. They said, they never got a breakdown...even though the electrician told me that they went through everything line item by line item.
The question:
The plumbing:
Was a nice to have. If they do not want to do thats fine.
The electrical:
They are going to put 12 plugs per breaker. This means in my new 40 breaker panel (which I paid extra for), I am going to get 16 breakers.
So, this means, all the bedroom plugs will all be tied together. The kitchen will have two stripes of plugs in it, instead of every other plug being a different circuit. That is, you have 2 walls
Their way:
wall one, has circuit A then A, wall two has circuit B then B.
My way:
wall one, has circuit A then B, wall two has circuit B then A.
Each bedroom should be on it's own circuit. So, what I have asked them to do, is loop the wires. For each plug in the kitchen, tie them together in the basement. For each other room, loop them together into the attic, or through the floor into the basement (two floor home).
If they will not do this. What are my options?
I think I should drag wires on the weekend when they are not there (they told me I can't work on the house during the build)? If I do, how do I make sure it will pass inspection? If I do not touch ANY of their wiring, I don't think they can complain. However, Can I drag a wire, leave a service loop and put it in the junction box and just tape the end. Leave it dead? Should I try to drag it all the way to my panel? Should I just leave it going to a junction box in the attic/basement?
Any other suggestions?
--Dan